Utility specifications often describe connection requirements, a maximum or a particular operating condition. A wet test can show what a used monoblock draws while running a stated format. Agree on where each instrument measures and which loads are inside the boundary. An upstream compressor serving several machines cannot isolate one monoblock without a suitable measurement point.
Build a utility log by operating phase
| Phase | Record with readings | What to compare with site data |
|---|---|---|
| Standby before the wet run | Duration, equipment energised, air pressure at inlet and meter points | Baseline and other services sharing a feed |
| Steady run on reference format | Accepted rate, water meter start/end, average power and air flow with its reference conditions | Demand during the agreed format and available connection capacity |
| Stopping and returning to steady running | Time, duration, depressed inlet pressure or short power and air peaks | Peak handling and limitations under simultaneous plant loads |
| Separate cleaning activity, if included | Duration and agreed metering point, with water volume and supply conditions | Cleaning utility demand separately from regular output |
Record units and convert only compatible figures
As an illustration, a water meter rising from 215.2 m³ to 215.5 m³ over 20 steady minutes records 0.3 m³, equivalent to an average of 0.9 m³/h in that interval. This figure describes that one supply and test phase. Record electrical energy in kWh separately from power in kW. For air, keep inlet pressure and the flow meter’s reference conditions with each reading. Have qualified site and supplier personnel determine measurement access and any conditions that cannot be reproduced. Bring the signed log and site utility data to the equipment review.
Add the measured utilities and unexplained peaks to the used monoblock inspection record so the installation team can distinguish a tested load from a supplier estimate.