Measure utility demand on a used monoblock during a wet test

Record water, compressed air and electricity in separate phases of a used monoblock wet test for a meaningful site check.

Italiano

Utility specifications often describe connection requirements, a maximum or a particular operating condition. A wet test can show what a used monoblock draws while running a stated format. Agree on where each instrument measures and which loads are inside the boundary. An upstream compressor serving several machines cannot isolate one monoblock without a suitable measurement point.

Build a utility log by operating phase

Worksheet for a witnessed wet test
PhaseRecord with readingsWhat to compare with site data
Standby before the wet runDuration, equipment energised, air pressure at inlet and meter pointsBaseline and other services sharing a feed
Steady run on reference formatAccepted rate, water meter start/end, average power and air flow with its reference conditionsDemand during the agreed format and available connection capacity
Stopping and returning to steady runningTime, duration, depressed inlet pressure or short power and air peaksPeak handling and limitations under simultaneous plant loads
Separate cleaning activity, if includedDuration and agreed metering point, with water volume and supply conditionsCleaning utility demand separately from regular output

Record units and convert only compatible figures

As an illustration, a water meter rising from 215.2 m³ to 215.5 m³ over 20 steady minutes records 0.3 m³, equivalent to an average of 0.9 m³/h in that interval. This figure describes that one supply and test phase. Record electrical energy in kWh separately from power in kW. For air, keep inlet pressure and the flow meter’s reference conditions with each reading. Have qualified site and supplier personnel determine measurement access and any conditions that cannot be reproduced. Bring the signed log and site utility data to the equipment review.

Add the measured utilities and unexplained peaks to the used monoblock inspection record so the installation team can distinguish a tested load from a supplier estimate.